Dateline: June 7, 2001 County looking to keep project on budget Roger Estlack, Clarendon Enterprise The
restoration of the Donley County Courthouse is one month behind schedule,
but the cause of the delay is an effort to keep the project on budget. County
officials had hoped to begin advertising for bids last month. Now they
hope to start advertising next week, according to County Judge Jack Hall. Representatives
from architectural firm Volz & Associates will meet with commissioners
in a called meeting this Friday at 1:30 p.m. in the Courthouse Annex to
discuss the project. Hall
said the architects have been busy in recent weeks seeking approval from
the Texas Historical Commission (THC) for cost cutting measures in case
bids for the $3 million project come in too high. “They
want to get approval ahead of time, otherwise it would be a long process
after the bids come in,” Hall said. The
county and its architects are concerned because bids for other courthouse
projects around the state have come in over budget. Hall said Llano
County’s bids came in about $500,000 over budget, and last month The
Rockdale Reporter said bids for Milam County’s project were
approximately $300,000 over expectations. Donley
County hopes to avoid a similar situation with the local project by
incorporating options – called “deductive alternates” – in the
bidding process that would allow commissioners to keep the restoration
within budget but not affect the restored outward appearance of the 1890
building. Some
items that may be looked at could include roofing materials, the use of
cast-stone versus quarried stone, below-grade waterproofing near the
courthouse’s foundation, or chimney reconstructions. The county may also
have to look at not finishing the interior of the third-story tower and
dormers, which were torn off in 1937 and will be reconstructed. County
officials are also hopeful that bids from area construction companies may
be more competitive than those received by counties downstate. “This
may go to bid and everything be fine,” architect Chris Hutson told
county commissioners in April, “but I would rather prepare for it now
than [the county] be hit with sticker shock when the bids come in.” For
more information about the Donley County Courthouse project, click
here.
|
|