|
Dateline: March 7,
2002
Courthouse
project on track for fall finish
By
Roger Estlack, Clarendon Enterprise
Restoration
of the Donley County Courthouse is still on track; and nearly all of the
structural work is finished, according to Phoenix 1 project manager
Stephen Dodge.
Phoenix’s
schedule calls for the building to be completed in September. The
company’s contract with the county calls for finishing in October.
Meeting
last Friday with project architect Chris Hutson, grant administrator John
Kiehl, and key contractors, Dodge reported that mechanical systems are
still being installed in the courthouse basement, but most of the wood and
steel framing is finished in the building. Also ice and water shielding
has been installed on the roof.
Stripping
of woodwork continues, but some areas are ready to begin finish work. A
sample stain has been applied to a section of wainscoting in the main
corridor.
The
new mechanical room on the third floor should be ready to accommodate new
heating, ventilation, and air-conditioning equipment this week; and
refinished windows and trim should begin returning this month.
Replacing
and repairing exterior metal cornices should begin within six to eight
weeks, Dodge said.
Brick
and mortar colors are still being matched. Curved brick for the circular
tower on the southeast corner will have to be special ordered. Officials
are also investigating to see if the chemical which is intended for
cleaning the existing bricks is safe to use on the sandstone elements of
the building.
In
other project news, county fundraising efforts have collected $15,959 from
persons and businesses interested in helping the project. Donations of any
size are greatly needed and appreciated and can be sent to the Donley
County Courthouse Preservation Fund, PO Box 825, Clarendon, TX 79226.
|