|
Dateline: April 25,
2002
County
seeks to meet $50k grant challenge
By
Roger Estlack, Clarendon Enterprise
All
deferred items have been added back into the Donley County Courthouse
Restoration project thanks to numerous donations. Now officials say the
county has an opportunity to begin putting items back in the job that were
originally deleted from the contract.
The
opportunity has been made possible by a challenge grant that will match
new contributions dollar for dollar up to a total of $50,000.
“We’re
extremely grateful for all the donations we’ve received thus far,”
Donley County Historical Commission Chair Jean Stavenhagen said. “With
this challenge grant, any new donations will be doubled. A $100 donation
will become $200, and a $1,000 donation will become $2,000. Your money
will go twice as far to finish the project and restore the Donley County
Courthouse as the Jewel of the Plains.”
If
this new grant challenge is met, decorative metal roof ornaments and the
replacement of deteriorating exterior stonework will be put back into the
project
Some
of the formerly deferred items which have been reinstated thanks to
successful fundraising include sanding and refinishing wood floors, carpet
for offices, refinishing stairs, restoring and refinishing doors and
transoms, repairing the tile floor in the main corridor, painting, and
metal doors in the basement.
Major
funding for the restoration project was obtained in 2000 through the Texas
Historical Commission (THC), but for the past six months, Donley County
Commissioners have been struggling to find a way to fully fund the
restoration the 1890 Donley County Courthouse after the lowest bid
exceeded the estimate prepared by the architect by nearly $1 million.
In
order to bring the cost down, Commissioners reduced the scope of the
project and then deferred other work until April 15, 2002. Thanks to the
generous contributions of individuals, businesses, and organizations,
county commissioners met in a called session last Monday and added the
deferred work back into the construction.
Those
interested in supporting this historic restoration are asked to contact
Jean Stavenhagen at (806) 874-3905. Donations of any size may be sent to
the Donley County Courthouse Preservation Fund, PO Box 825, Clarendon, TX
79226.
In
other courthouse project news, interior work on the Donley County
Courthouse is coming along rapidly, Phoenix I project manager Stephen
Dodge said at a construction conference last Friday.
Fifty
percent of the trim work and 75 to 80 percent of the rough-in has been
done on the first floor. Most of the trim has been finished on the second
floor and is ready for plaster. Mechanical work continues in the basement
and on the third floor.
Plastering
is nearly complete on second floor rooms east of the courtroom, and the
courtroom itself should get a third coat of plaster this week.
Paint
and stain colors will be chosen soon. Architects with Volz &
Associates were here Friday to gather paint chip samples. They will do a
microscopic analysis to attempt to deduce the original colors used in the
building.
Woodwork
used in the courthouse has finally been positively identified. It is a
Colorado white pine trim with California redwood panels. Project officials
agreed the California redwood is rarely found in Texas courthouses, and
head carpentry subcontractor Richard Oberhaus believes the original
builders were heavily influenced by their work in Colorado.
Architect
John Volz says the Donley courthouse will be one of the most beautiful his
firm as worked on because of the woodwork in the building.
Trenches
for utilities are expected to be dug in the next two weeks, and AEP set
new transformers for the building on Monday.
Subcontractors
are currently working to resolve sizing problems with HVAC floor grilles
and recessed electric fixtures on the first floor.
The
Texas Historical Commission has disallowed the use of ceiling fans in the
district courtroom since they were not original. The architects believe
the air-conditioning system should provide sufficient airflow.
One
area where the project in danger of falling behind schedule is the masonry
work as contractors continue to look for a replacement brick. Acme brick
in Tulsa, Okla., was reported to be the only manufacturer interested in
the job. That company purchased new forms to make the right size brick.
The
color of the new bricks is close, but the bricks have a sheen to them.
Volz is looking into a new European micro-abrasion technique that might
age the brick slightly to remove the sheen.
Repairs
on masonry behind the metal cornices is on hold awaiting a report from a
structural engineer. Water damage of the last century has loosened some of
the facing brick and contributed to the deterioration of the backing
brick.
|