|
Dateline: November
14,
2002
Greenbelt
begins filter plant upgrade
By Roger Estlack,
Clarendon Enterprise
Improvements
are getting underway at Greenbelt Water Authority which will change the
way Clarendon’s drinking water is treated.
Greenbelt
General Manager Bobbie Kidd said work on the $2.3 million project at the
filter plant north of Clarendon will be performed by the firm of R.M.
Wright of El Paso.
“They
have already been here and rented two houses for their workers to stay
in,” Kidd said. “They are just waiting for material to be delivered to
get started.”
The
project will completely change Greenbelt’s chemical feed system,
disinfecting system, filtering process, and reporting process, Kidd said.
Half of the money spent at the plant will go toward replacing the old
filters which have been in place for 35 years.
The
water authority has until 2004 to comply with more stringent standards set
by the federal government. Kidd said Greenbelt started the process of
upgrading several years ago.
“Three
years ago in October we started with a 12-month evaluation to identify any
problems and what needs to be done to meet the new standards,” he said.
“We also tried to anticipate the regulations which might be enacted in
the next 20 years.”
The
new system will change the treatment of Greenbelt water from a chlorine
method to a new treatment by chloramines, which uses both chlorine and
ammonia. The system will also
stop using dry bulk chemicals and move to liquid chemicals.
Other
changes include doubling the electrical service at the plant from 500 KVA
to 1,000 KVA and upgrading the computer system in the plant which controls
treatment of the water and delivery of the water from the Greenbelt
Reservoir from here to Crowell. The present controls were last upgraded 19
years ago, and some parts date back to 1965.
Kidd
said the contractor expects to be finished by May 1, 2003, although the
contract allows for 56 weeks to complete the job.
Local
residents should not have any disruption in their water service during
most of the work. But Kidd did say there will be one day next spring that
water won’t be pumped to Clarendon. The authority will work with the
City of Clarendon to notify customers before that happens.
“If
we can pick that day and can pump the water tanks full ahead of time,
there should be no problem.”
Greenbelt
is also building a new storage tank at Childress as part of the upgrade.
The Natgun Corporation was awarded the $1.7 million contract for that job
and expects to be finished next July, although they also have a 56-week
contract.
Natgun,
which is based in Wakefield, Mass., with offices in Dallas, is
constructing a new six million gallon concrete tank to replace the old
four million gallon steel tank presently in Childress.
Site
work has already been completed on that job, Kidd said.
Financing
for the project was secured for the project in 2001, and Kidd said the
bids have come in lower than expected, which will allow Greenbelt to do
some additional work.
Engineering
for the filter upgrade and the new tank is under the supervision of Freese
and Nichols, Inc. – the same firm which designed the Greenbelt Reservoir
and the filter plant in the 1960s.
|