|
Dateline: January 23,
2003
Chimney
issue slows progress on courthouse
By Roger Estlack, Clarendon Enterprise
Work
on the exterior of the 1890 Courthouse continues at a slow pace as Donley
County representatives negotiate chimney heights with the Texas Historical
Commission.
Stephen
Dodge of Phoenix I Restoration said in a construction conference last
Wednesday that rebuilding a chimney on the northwest side of the building
is keeping the roof from being completed.
“The
roof has to be put on left to right, and we can’t go further until the
temporary bracing on the chimneys is removed and this other chimney is
finished,” Dodge said.
The
northwest chimney was missing prior to the current restoration project,
which restored it to a height of 23 feet above the roofline. But the poor
condition of the original supporting masonry and unknown original
construction conditions caused the chimney to collapse in November,
knocking a hole in the roof and sending an 8,000 lb. section crashing into
the scaffolding around the courthouse.
A
subsequent report from the structural engineer on the project has
recommended the chimney and its twin on the northeast corner be lowered
from 23 feet to 17 feet to reduce weight load and wind load on the
structures. The Texas Historical Commission, however, has not approved the
design change.
“The
THC believes this to be a restoration project, and we’re going to
require the chimneys to be put back like they were,” said THC’s Lyman
Labry.
County
Judge Jack Hall said the county was not in favor of the chimneys being the
original height due to safety concerns. It was a point echoed by project
architect Chris Hutson of Volz & Associates.
“We’ve
all learned now that masonry deteriorates over time,” Hutson said.
“We’re not going to put our professional license at stake here.”
Labry
said the THC was not unsympathetic to the county’s position but that his
agency believed the engineer should be able to come up with a design that
meets the original height and is safe.
Judge
Hall said this week the engineer has a new plan to allow the chimneys to
be rebuilt to 20 feet. That plan is pending THC approval.
Meanwhile,
work is progressing on the interior of the building. Dodge said last week
the ceilings are 75 percent done and the carpentry work is 96 percent
finished. Staining of woodwork is “substantially completed” with only
touch up work remaining.
Replacement
tiles for the main corridor are being manufactured now, and painting of
the interior walls and ceilings are coming along well.
Dodge
also said workers are ready to proceed with bricking the third floor of
the tile. Much of the new stonework is also now on site. Some of the stone
is manufactured, and real stone quarried in Kansas will be used near the
entrance.
County
officials are still waiting for pricing information to determine what
formerly deleted work to add back to the project. A completion date cannot
be set until all change orders have been issued.
|