Dateline: December 7,
2006
TxDOT
to replace culverts on US 287
CHILDRESS – The
Texas Department of Transportation (TxDOT) held a pre-construction meeting
on Wednesday, November 29, at the Donley County Maintenance Office near
Clarendon to discuss a project to install new safety end treatments
(culverts) on US 287 from Hedley to the Armstrong County line.
The contractor for
this $1.1 million project is J. Lee Milligan of Amarillo, TX. The length of this project is 27.3 miles long with 168
working days scheduled with weather permitting.
The contractor will
install safety end treatments along the route –replacing the upright
concrete headwalls with sloping headwalls and covering the openings with
steel pipe runners that allow water to run freely, but enable a vehicle to
cross the opening without plunging into the mouth of the culvert.
“Drivers who run
off the road and live to tell the story may owe their lives to safety
features like this”, said Tracy Cain, Wellington Area Engineer.
“Safety is our primary concern, and this feature will be much safer in
run off the road accidents.”
The project
superintendent for J. Lee Milligan is Lester Shaver, and Darl Eigenmann is
the chief inspector for TxDOT.
There will be no lane
closures during the duration of this project.
“The contractor
will need to cone off the shoulders in a few places.
Otherwise this project will not affect the traveling public,”
Cain said.
For more information, call Barbara Seal at (940)
937-7145.
|